Weeks 1-2: Excavation & Foundation (2 weeks)

Weeks 3-5: Framing (3 weeks)

Weeks 6-8: Mechanical Rough-in (3 weeks)

Weeks 9-11: Insulation & Drywall (3 weeks)

Weeks 12-15: Interior Trim & Paint (4 weeks)

Weeks 16-17: Hard Surface Flooring & Cabinets (2 week)

Weeks 18-21: Carpet & Cleaning (4 weeks)

Weeks 22-24: Final Walk-Thru & Closing (3 weeks)

*Note: This is a general 24-week timeline - all homes may not fit this exact schedule. Most decisions are required prior to starting each house. All final interior details and color selections will be made by week six.